Costs rise and delays lengthen in North Sydney Olympic Pool rebuild project

Costs rise and delays lengthen in North Sydney Olympic Pool rebuild project
May 9, 2023

The redevelopment of the North Sydney Olympic Pool is unlikely to see the facility reopen until April 2024 - 18 months later than originally planned - while project costs have increased by more than $30 million with total spending on the rebuild set to reach at least $89 million.

The latest example of building costs at a Sydney aquatic facility going massively over budget, a report on problems with the project was presented to local North Sydney Councillors at a meeting last week.

The independent report, commissioned by the Council last October and conducted by consultants PwC, detailed the multimillion-dollar cost blowouts and delays to the controversial redevelopment of famous Olympic swimming pool that sits beneath the Sydney Harbour Bridge.

North Sydney Councillor MaryAnn Beregi, a long-time critic of the project, told the Council meeting last week that the report “absolutely vindicates everything I said in the last council with this project”.

“It was handled appallingly. I hold my tongue when I say, I told you so, but I did.

“We tried and tried to call the majority of the former council to at least listen, and to hear what we had to say, which was only in the best interests of North Sydney and the ratepayers.”

The PwC review, found the $64 million budget did not consider all costs associated with project, such as internal project management, equipment and fit-outs, and did not provide sufficient contingency. The review was also critical of the council’s decision to manage the large and complex project internally, and its rush to sign the construction contract with developer Icon on New Year’s Eve in 2020.

Councillor Jilly Gibson, who was Mayor when the redevelopment was approved, said the review was flawed and omitted relevant information.

Gibson said the consultants’ report had “grossly” underestimated the effects of the pandemic and La Nina on the budget and timeframe, and focused on “everything that they thought had gone wrong”.

Independent Mayor Zoe Baker, who raised concerns about the scale of the project as a Councillor, said the findings of the independent review were “unfortunately not a surprise”, noting that they would “act as a catalyst for the current council to address the cost overruns and time delays”.

Work on the redevelopment - which includes upgrades to the indoor and outdoor pools, and building a new 970-seat grandstand, children’s water play area and expanded gym - began in March 2021.

In 2020, the Council said that the cost to ratepayers of the redevelopment had ballooned from $58 million to at least $64 million.

At that time, the rebuild was expected to be completed in November 2022.

Opened in 1936, the North Sydney Olympic Pool took 36 weeks to build and cost £47,000, about $12 million today.

It was the first pool in Australia to purify sea water and used advanced technology for the time.

It hosted the Empire Games in 1938 and 1958, and 86 world records in swimming and diving have been set in the pool.

Images: Work in progress on the North Sydney Olympic Pool (top) and the concept for how the facility will look when the rebuild is complete (below).

Related Articles

28th April 2023 - New draft guidelines released on managing child safety in aquatic facilities

21st April 2023 - Foundation memberships on offer at Parramatta’s new Aquatic Centre

18th April 2023 - Aquatic and Recreation Institute appoints new Executive Officer, announces Graham Arnold as 2023 conference program keynote

11th April 2023 - Latest PwC Global Sports Survey identifies major events driving industry growth

29th March 2023 - Envibe helps Lake Macquarie swim centres deliver impressive aquatic experiences

1st November 2022 - North Sydney Council calls for independent review of Olympic Pool redevelopment

20th September 2022 - Delays and rising costs impact North Sydney Olympic Pool redevelopment

4th December 2021 - PwC Chief Executive backs proposed Darwin stadium in support of Northern Territory AFL team

13th January 2021 - Builder appointed for North Sydney Olympic Pool redevelopment

11th January 2021 - Cost of City of Sydney’s new Gunyama Aquatic Centre set to exceed $100 million

11th April 2020 - Council moves forward with plans to redevelop North Sydney Olympic Pool

27th February 2020 - North Sydney Olympic Pool classed as a ‘regional facility’ when gaining Federal grant funding

27th March 2019 - North Sydney Olympic Pool refurbishment needs another $30 million

12th August 2018 - PwC report says Sydney is ‘no fun’ for residents

12th August 2015 - Sydney’s costly affair with extravagant aquatic centres


Support our industry news service
We hope that you value the news that we publish so while you're here can we ask for your support?

As an independent publisher, we need reader support for our industry news gathering so ask that - if you don't already do so - you back us by subscribing to the printed Australasian Leisure Management magazine and/or our online news.

 

supplier directory

The Complete Guide to Leisure Industry Products & Services.

See the directory see all

Smart Connection Consultancy

Smart Connection Consultancy is a boutique sport and recreation consultancy who has become one of Australia’s leading advocates for the use of synthetic sports surfaces as a vehicle to grow…

read more

Consultants / Recreation / Sport / Surfaces

 
 

SimplySwim

    SimplySwim is a school management solution that helps swimming school owners and managers optimize operations by automating functions such as managing class schedules, billing and…

read more

Aquatics / Education / Recreation / Safety / Technology

 
 

Again Faster

ABOUT Again Faster is a Brisbane based, Australian owned supplier of strength and conditioning and functional fitness equipment. With nearly 10 years experience in the Australian market, we are…

read more

Fitness / Recreation

 
 

Mattioli

Gianni Mattoli Director 0412 360 378 E: gianni@mattoli.com.au E: marketing@mattioli.com.au Tony Aloi National Operations Manager 0425 762 864 E: tony@mattoli.com.au MEL · SYD · ADE…

read more

Aquatics / Recreation / Safety / Technology

 
 

24/7 Software

The world's greatest properties run on 24/7 Software Whether at commercial properties, corporate facilities, sports arenas, or public entertainment venues, we're proud to lead the way in…

read more

Entertainment / Security / Sport / Technology / Venues

 
 

SeatGeek Asia Pacific

SeatGeek is a search engine and mobile-focused ticket marketplace that allows fans to buy and sell tickets for live events. As of August 2018, SeatGeek has exited the Australian, New…

read more

Entertainment / Sport / Technology / Ticketing / Venues

 
 

InterQuad (International Quadratics) 

InterQuad (International Quadratics)  With a combined legacy spanning over 150 years, International Quadratics (founded in 1976) and Pierce Pool Supplies (originally established in 1898 as A H…

read more

Aquatics / Safety / Technology / Waterparks

 
 

The Jump Pad

The Jump Pad is a safe, flat inflatable made in a variety of sizes which can be used indoor or outdoor. From 3mx3m up to a whopping 9mx21m. Markets include Indoor and outdoor playgrounds, schools,…

read more

Attractions / Entertainment / Play

 
 
 
 

get listed with our suppliers directory

Get your business noticed in our targeted directory. Viewed by 10,000 industry professionals per week!

list your business