Having received a strong favourable response from the public, Christchurch City Council has voted to increase the budget for the city’s multi-use arena to $683 million and will commit to a design and construction contract with lead contractor BESIX Watpac that will see building get under way by the year’s end.

Back in 2020, Christchurch City Council and the New Zealand Government formally signed off on a joint funding agreement for the city’s new multi-use arena with both parties having agreed to contribute a total $473 million towards the cost of the new venue, with the Council committing $253 million and the Crown $220 million.

Moving forward, following Council's decision to increase the budget, BESIX Watpac Chief Executive Mark Baker notes the stadium will be one of only two in the world with a fully enclosed roof and natural grass playing field. The stadium will also be built to withstand Christchurch seismic activity not only on completion but during construction.

Council is also future-proofing this world-class entertainment venue for Esports.

Te Kaha Project Delivery Limited were able to secure a fixed price contract for the design and construction of the arena, which means the Council is protected from the risk of further cost escalations.

Christchurch Mayor Lianne Dalziel advised  “Christchurch is the largest city in the South Island and it should have a multi-use arena where top international acts can perform and the All Blacks, the Crusaders and other sporting greats can play. We also need to be preparing for the future of entertainment and Esports is taking off around the world.

“That was the strong message we got from the public during the consultation process.

“The cost of the arena is much higher than we envisaged when we first began planning for this project. But no-one could have foreseen the global events – the COVID-19 pandemic and the war in Europe – which have disrupted supply chains, pushed-up commodity prices and led to an over-heated construction market.

“The reality is that we cannot build the type of multi-use arena that we want for Christchurch for the money that we have on the books. Unless we are willing to significantly scale back the size and scope of the arena, we have to increase the budget.

Mayor Dalziel thanked the Te Kaha Board for all the work they have done in giving Council “certainty on the costs, scale and scope of the project, which means the Council is now in a position to enter into a contract with BESIX Watpac so they and the Kōtui Consortium can get on with the job of building us a world-class multi-use arena in the heart of our city.”

Mayor Dalziel added “with this arena, the days of Christchurch being bypassed for big entertainment and sporting events will be over.

“We are also future-proofing this world-class entertainment venue for Esports, which in terms of global audience is on an exponential curve. You can have 30,000 people in a stadium and millions online, all participating in the same event.’’

BESIX Watpac Chief Executive Mark Baker says the decision to move ahead with the project and realise the Council vision for a landmark multi-use stadium, capable of facilitating world-class sporting matches and international entertainment acts, will be celebrated now and into the future.

Baker says BESIX Watpac will continue to work with Christchurch City Council and Te Kaha Project Delivery Limited to closely manage the delivery and the construction timetable.

The company has already let trade packages for early works and will continue to lock-in local trades and suppliers early to secure works certainty and manage cost well ahead of the construction schedule.

Image: Credit Christchurch City Council 

Related Articles

14th July 2022 - Fixed price negotiated for design and construction of Christchurch multi-use arena, Te Kaha

8th July 2022 - Submissions indicate strong support for increasing budget of Christchurch multi-use arena

15th June 2022 - Christchurch City Council to consult public about extra money required for multi-use arena

1st June 2022 - Costs to build Christchurch’s multi-use arena could escalate by up to $150 million

17th February 2022 - Chief Executive appointed for company overseeing delivery of Canterbury Multi-Use Arena

28th January 2022 - New name and design released for Canterbury Multi-Use Arena

23rd December 2021 - Noise management rules approved for Canterbury Multi-Use Arena

25th October 2021 - Mid-2025 completion date estimated for Canterbury Multi-Use Arena

9th September 2021 - Naylor Love Canterbury appointed to build new multi-use centre in Christchurch

13th August 2021 - Christchurch City Council decides to restore extra 5000 seats for Canterbury Multi-Use Arena

21st July 2021 - Christchurch City Council to vote on design direction for Canterbury Multi-Use Arena

10th June 2021 - Canterbury Multi-Use Arena noise management rules ready for Ministerial approval

30th March 2021 - Australian-led consortium to build Christchurch’s multi-use arena

27th January 2021 - Port Hedland Council approves funds for JD Hardie Youth and Community Hub multi-user courts

5th October 2020 - $473 million joint funding agreement agreed for new Christchurch multi-use arena


Support our industry news service
We hope that you value the news that we publish so while you're here can we ask for your support?

As an independent publisher, we need reader support for our industry news gathering so ask that - if you don't already do so - you back us by subscribing to the printed Australasian Leisure Management magazine and/or our online news.

 

supplier directory

The Complete Guide to Leisure Industry Products & Services.

See the directory see all

Summit Fitness

Summit Fitness Equipment is now part of NovoFit - see www.ausleisure.com.au/suppliers/novofit/

read more

Fitness / Recreation / Technology / Wellness

 
 

GREENEDESK

Track. Engage. Retain GreeneDesk is a suite of cloud based software solutions helping health clubs, leisure centres and swim schools to effectively track progression, improve customer engagement and…

read more

Aquatics / Billing / Education / Fitness / Technology

 
 

Clubware

Clubware’s online gym software is not your run of the mill management system. It has been carefully designed to incorporate all the elements that a fitness club would need. How did we do that?…

read more

Access / Billing / Fitness / Recreation

 
 

Polin Waterparks

Polin was founded in Istanbul in 1976, and has since grown into a leading company in the waterparks industry. Today Polin is one of the world leaders in the design, production, and installation of…

read more

Aquatics / Attractions / Play / Waterparks

 
 

Myzone

Email for trade enquiries: Enquiriesapac@myzone.org  Customer support desk - Click Myzone support or go to ‘help’ on myzone app to access live support. Myzone® is the leading…

read more

Fitness / Sport / Technology / Wellness

 
 

HIB Insurance Brokers Pty Ltd

HIB Insurance Brokers - Experts in Leisure and Amusement Insurance With over 20 years specialising in the Amusement and Leisure industries, we have the experience to understand your operations and…

read more

Attractions / Entertainment / Insurance / Recreation / Safety

 
 

SENtag

Developed in Europe, this innovative system offers a safety management solution for swimming pools that checks individual swimmers via their wristband - monitoring their depth and time. Sensors…

read more

Aquatics / Hospitality / Safety / Technology / Waterparks

 
 

Abel Sports

INTRODUCTION Abel Sports is Australia’s leading manufacturer and suppliers of Goal Posts, sports ground safety netting systems and coaches boxes for Stadiums ,Sports Clubs, Councils and…

read more

Recreation / Sport / Venues

 
 
 
 

get listed with our suppliers directory

Get your business noticed in our targeted directory. Viewed by 10,000 industry professionals per week!

list your business